On May 10, 12:17 pm, Michael Merlin <[email protected]>
wrote:
> Sometimes I want to move a task from my to a Project that I have not
> yet entered.
>
> e.g.
>
> I do Ctrl+M to move the current task
>
> if the project (that I want to move this current task under) has not
> been created yet, then I need to
> cancel the current Task move operation,
> return to the main tree,
> create the new Project,
> navigate back to the current Task,
> and move this current task to under the new Project
>
> i.e.  Move (Ctrl+M) currently only allows moving a task to a pre-
> existing task/project.
> I would like the ability to create a parent task/project on the fly,
> while doing a Ctrl+M move curren task
--~--~---------~--~----~------------~-------~--~----~
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to 
[email protected]
For more options, visit this group at 
http://groups.google.com/group/myLifeOrganized?hl=en
-~----------~----~----~----~------~----~------~--~---

Reply via email to