@chuckdevee

At least a "workaround" ... set hotkeys for "previous day" and "next
day" (I'm having those on "+" and "-" on my num pad) ... then you'll
be able to do it by key commands.

Maybe helful?

Eberhard

On 29 Jul., 08:55, chuckdevee <[email protected]> wrote:
> In the Timing and Reminder section of the properties pane, there are
> three really useful shortcuts above the dates: 'today', 'next day' and
> 'next week'. Now that I can multi-select tasks, I can highlight an
> entire set of subtasks, all dates different, and shift their dates
> together. For example, I might set out a project that should take me a
> week to complete - say, 14 tasks, 2 on each day. But if I shelve the
> project (by removing from to-do list view) and then decide to do it at
> a later date, or if I simply fall behind on it, I can shift the dates
> of all the subtasks together by selecting all the subtasks together
> and using these shortcuts to shift the dates to the present. It works
> really well, especially for projects that I have got behind on.
>
> It would be useful also to have the option to move dates BACKWARDS as
> well, in similar fashion, by having a shortcut, 'previous day' as
> well. Ths would be useful for bringing forward projects that I had
> scheduled in the future.
--~--~---------~--~----~------------~-------~--~----~
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to 
[email protected]
For more options, visit this group at 
http://groups.google.com/group/myLifeOrganized?hl=en
-~----------~----~----~----~------~----~------~--~---

Reply via email to