I find it useful to post a folder as a dependency. The folder is a
project. The dependency is not completed until the project is
completed.

When the project is completed the dependency is removed. This is a
useful capability. I would hate to see it removed.

Mark

On Dec 1, 1:48 pm, chuckdevee <[email protected]> wrote:
> When adding dependencies to a task, in the view that opens up entitled
> 'Select tasks current task depend on', there is no indication of
> whether these tasks are folders - ie whether they can actually be
> completed. Hence if someone creates a task dependency against a folder
> by mistake, then the task could forever remain invisible from the To-
> Do view!
>
> I'd suggest that the tickboxes are actually shown in this dependency
> view - although obviously without the ability to actually complete the
> selected task.
>
> In fact, as the dependency relates to the completion box of a target
> task, perhaps when a task is selected in this view, a red 'D' shows in
> the tickbox to indicate a task is dependent on its completion - just
> an idea.
>
> One other thought, the title for this view, 'Select tasks current task
> depend on'  should instead be 'Select tasks current task depends
> on'  (ie depend should be plural). In fact, I'd suggest it might be
> clearer to have the title as:-
>
> "Select tasks on which the current task depends"
> or
> "The current task depends on the completion of tasks selected below"

--

You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/mylifeorganized?hl=en.


Reply via email to