Alyona, The parent project's "Time Required Max" column does not represent the sum of its child's' combined "Time Required Max" fields. Is there some way a folder or project can display the sum of its child's "Time Required Max" fields summed as a column?
Thanks, Daniel On Friday, November 10, 2017 at 12:18:05 AM UTC-6, Alyona (MLO Support) wrote: > > Hello, > > If you convert a parent task to a project, MLO will show you the total > time based on the "Time Required Max" values of the subtasks. > > > On Thursday, November 9, 2017 at 10:17:32 AM UTC+2, [email protected] > <javascript:> wrote: >> >> Hello! >> >> I would like a parent item to display the sum of its children's "Time >> Required Max" fields. I'm wanting to have items within a project have >> individual time estimates that I can view a summary of at the >> project/parent level. >> >> Does this functionality exist, or do you recommend a better approach? >> >> Thank you, >> Daniel >> > -- You received this message because you are subscribed to the Google Groups "MyLifeOrganized" group. To unsubscribe from this group and stop receiving emails from it, send an email to [email protected]. To post to this group, send email to [email protected]. Visit this group at https://groups.google.com/group/mylifeorganized. To view this discussion on the web visit https://groups.google.com/d/msgid/mylifeorganized/a3ea5568-6b02-4ffa-8e39-a64dfceeb77b%40googlegroups.com. For more options, visit https://groups.google.com/d/optout.