https://issues.apache.org/jira/browse/OAK-3461?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
]
Francesco Mari resolved OAK-3461.
---------------------------------
Resolution: Fixed
Fix Version/s: 1.3.7
Fixed in trunk at r1705977.
> Run m-bundle-p:baseline before integration tests
> ------------------------------------------------
>
> Key: OAK-3461
> URL: https://issues.apache.org/jira/browse/OAK-3461
> Project: Jackrabbit Oak
> Issue Type: Improvement
> Components: parent
> Reporter: Francesco Mari
> Assignee: Francesco Mari
> Fix For: 1.3.7
>
>
> The baseline goal of the maven-bundle-plugin is currently bound to the verify
> phase (as per default). It should be bound to the pre-integration-test phase
> to give it a possibility to fail before integration tests are executed.
--