> > Kilo Design Summit: Nov 4-7
> > Kilo-1 milestone: Dec 11
> > Kilo-2 milestone: Jan 29
> > Kilo-3 milestone, feature freeze: March 12
> > 2015.1 ("Kilo") release: Apr 23
> > L Design Summit: May 18-22
>
> Following feedback on the mailing-list and at the cross-project meeting,
> there is growing consensus that shifting one week to the right would be
> better. It makes for a short L cycle, but avoids losing 3 weeks between
> Kilo release and L design summit. That gives:
>
> Kilo Design Summit: Nov 4-7
> Kilo-1 milestone: Dec 18
> Kilo-2 milestone: Feb 5
> Kilo-3 milestone, feature freeze: Mar 19
> 2015.1 ("Kilo") release: Apr 30
> L Design Summit: May 18-22
>
> If you prefer a picture, see attached PDF.
>
> --
> Thierry Carrez (ttx)
>

+1
_______________________________________________
OpenStack-dev mailing list
OpenStack-dev@lists.openstack.org
http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev

Reply via email to