On Thu, Mar 12, 2009 at 12:24 PM, revDAVE <c...@hosting4days.com> wrote:
> Hi folks,
>
> My goal was to create a dynamic date related list as follows:
>
> - take the current date (3/12/2009)
> - create a new date from it which would be the *1st* of that month -
> (3/1/2009)
>
> - then create a list that shows the current and previous 11 months like:
>
> 03/1/09
> 02/1/09
> 01/1/09
> 12/1/08
> 11/1/08 etc...
>
>
>
> --- so I did this (not fancy but was working)
>
>
> $nowts = strtotime(date("m")."/1/".date("y"));
>
>
> $m01 = date('m',$nowts-(0))."/1/".date('y',$nowts-(0));
> $m02 = date('m',$nowts-(86400*30))."/1/".date('y',$nowts-(86400*30));
> $m03 = date('m',$nowts-(86400*60))."/1/".date('y',$nowts-(86400*60));
> $m04 = date('m',$nowts-(86400*90))."/1/".date('y',$nowts-(86400*90));
> $m05 = date('m',$nowts-(86400*120))."/1/".date('y',$nowts-(86400*120));
> $m06 = date('m',$nowts-(86400*150))."/1/".date('y',$nowts-(86400*150));
> $m07 = date('m',$nowts-(86400*180))."/1/".date('y',$nowts-(86400*180));
> $m08 = date('m',$nowts-(86400*210))."/1/".date('y',$nowts-(86400*210));
> $m09 = date('m',$nowts-(86400*240))."/1/".date('y',$nowts-(86400*240));
> $m10 = date('m',$nowts-(86400*270))."/1/".date('y',$nowts-(86400*270));
> $m11 = date('m',$nowts-(86400*300))."/1/".date('y',$nowts-(86400*300));
> $m12 = date('m',$nowts-(86400*330))."/1/".date('y',$nowts-(86400*330));
>
> PROBLEM: all was fine for the last few months but several days back the 1st
> few months were wrong - like this...
>
>
> 03/1/09
> 02/1/09
> 12/1/08 * wrong
> 12/1/08
> 11/1/08 etc...
>
> * I think the math went wrong because FEB had 28 days - not 30 (not sure why
> just 1 month JANUARY was wrong...)
> I temporarily fixed it with less than 30 day jumps like:
>
>
> $m01 = date('m',$nowts-(0))."/1/".date('y',$nowts-(0));
> $m02 = date('m',$nowts-(86400*28))."/1/".date('y',$nowts-(86400*28));
> $m03 = date('m',$nowts-(86400*58))."/1/".date('y',$nowts-(86400*58));
> $m04 = date('m',$nowts-(86400*88))."/1/".date('y',$nowts-(86400*88));
> $m05 = date('m',$nowts-(86400*118))."/1/".date('y',$nowts-(86400*118));
> $m06 = date('m',$nowts-(86400*150))."/1/".date('y',$nowts-(86400*150));
> $m07 = date('m',$nowts-(86400*180))."/1/".date('y',$nowts-(86400*180));
>
> Q: Any ideas how to fix this issue? (please try to keep it simple - 'cause I
> ain't no math wiz either)
>
>
>
> --
> Thanks - RevDave
> Cool @ hosting4days . com
> [db-lists 09]
>

Unless you are in a timezone that does not observe DST, you can't use
a constant 86400 as the number of seconds in a day. You could try
something like this:

<?php

$date = strtotime('-' . (date('d') - 1)  . ' days');

for ($i = -11; $i <= 0; ++$i) {
    $list[] = date('m/d/Y', strtotime("$i months", $date));
}

var_dump($list);

?>

Andrew

-- 
PHP General Mailing List (http://www.php.net/)
To unsubscribe, visit: http://www.php.net/unsub.php

Reply via email to