Sorry for the delay in replying ...

  rz> I had a similar problem happen to me this morning!  No tasks
  rz> were carried forward.  However, none of the project pages were
  rz> updated.  So the only new / updated file for me is
  rz> 2006.11.17.muse.

  rz>  1. I have not changed any planner or Emacs code.

Same with me.

  rz> Could we have something in our diaries that causes the planner
  rz> code to abort?

Maybe.  I'll leave that call to "the experts"!  ;-)

  rz> Okay, seriously.  For me, merely setting
  rz> planner-carry-tasks-forward to 2 fixed my problem.

I tried various values myself ...

Originally (like Michael suggests in a later post), I was using `7'.
When I got this problem, I changed it to something like `30'.  Another
time, I set it to `14'.  Each time, of course, restarting 'planner'.

It continues to be at `14'.

I just don't understand why the "day pages" didn't just find the older
entries in the "plan pages".  As noted before, the dated entries *are* there.

  rz> Good luck to you.

Thanks.

What I ended up doing was to simply re-enter the most important tasks
onto a "day page" (couldn't be without 'planner' that long!).  They
are being forwarded correctly.

My *hunch* is that I inadvertently deleted almost all tasks from the
current "daily page" and wrote it out twice (thus loosing any backup).
But, as I said above and earlier, I just don't understand why the
tasks weren't re-generated again off of the "plan pages".

Again sorry for the delay in my response ... some local (non-life
threatening) medical issues needed attention.

Thanks for your comments!

  -Kenneth