HNP Response:

The CAP program should be used to document the occurrence of:
a. Any section, unit or subunit exceeding its monthly goal.
b. The responsible section, unit or sub-unit will document, any work activity 
with an actual
dose equal to or greater than 10 mrem and is ± 25% (that is, plus or minus) of 
the
estimate. c. Any weekly dose projection activity greater than or equal to 50 
mrem with a dose delta of
+ 25% (that is, plus or minus).
d. The responsible section, unit or sub-unit will document, any work activity 
or weekly dose
projection which does not meet the above thresholds at management discretion to
capture lessons learned or improvement opportunities.


Michael Seabock
Lead Radiation Control Specialist - ALARA
Harris Nuclear Plant
919.362.2808 *
[email protected]


From: [email protected] [mailto:[email protected]] On Behalf Of 
LOLLIS, ANNE M
Sent: Monday, November 21, 2011 1:24 PM
To: [email protected]
Subject: Powernet: Criteria for Initiation of Condition Report for Deltas in 
ALARA Packages

Does your plant have specific criteria (such as a percentage or mrem 
difference) for initiating a condition report when it is identified that there 
is a delta between actual exposure and budgeted exposure for ALARA Packages?   
If so, what is the criteria that is used?


Thanks in advance for your help!

Anne Lollis
Fort Calhoun Nuclear Station

________________________________
This e-mail contains Omaha Public Power District's confidential and proprietary 
information and is for use only by the intended recipient. Unless explicitly 
stated otherwise, this e-mail is not a contract offer, amendment, or 
acceptance. If you are not the intended recipient you are notified that 
disclosing, copying, distributing or taking any action in reliance on the 
contents of this information is strictly prohibited.