WBN replies:

 

Outage goal is built into our business plan. At the beginning of the
year we justify our outage goals with our FY goals. At six months out we
begin our dose construction with work scope freeze. At 3 months out  we
present all our ALARA plans to the ALARA site committee for approval.,
this committee will meet at 2 months out and put the outage goal in
stone. The ALARA department will break the dose down from the planned
work to the respective departments. 

 

From: [email protected] [mailto:[email protected]] On Behalf
Of LOLLIS, ANNE M
Sent: Monday, April 02, 2012 2:02 PM
To: '[email protected]'
Subject: Powernet: Department Dose Goals during Refueling Outage

 

Just a quick question for you all...do you set department goals during
refueling outages?  I am benchmarking this for our ALARA Committee
because the question came up at a meeting.  We have department goals
during on-line, but have never had them during an RFO.  Thanks in
advance for your response.  It is greatly appreciated.

 

Anne Lollis

Supervisor-Radiation Protection

Fort Calhoun Nuclear Station

 

________________________________

This e-mail contains Omaha Public Power District's confidential and
proprietary information and is for use only by the intended recipient.
Unless explicitly stated otherwise, this e-mail is not a contract offer,
amendment, or acceptance. If you are not the intended recipient you are
notified that disclosing, copying, distributing or taking any action in
reliance on the contents of this information is strictly prohibited.

Reply via email to