WBN replies:
Outage goal is built into our business plan. At the beginning of the year we justify our outage goals with our FY goals. At six months out we begin our dose construction with work scope freeze. At 3 months out we present all our ALARA plans to the ALARA site committee for approval., this committee will meet at 2 months out and put the outage goal in stone. The ALARA department will break the dose down from the planned work to the respective departments. From: [email protected] [mailto:[email protected]] On Behalf Of LOLLIS, ANNE M Sent: Monday, April 02, 2012 2:02 PM To: '[email protected]' Subject: Powernet: Department Dose Goals during Refueling Outage Just a quick question for you all...do you set department goals during refueling outages? I am benchmarking this for our ALARA Committee because the question came up at a meeting. We have department goals during on-line, but have never had them during an RFO. Thanks in advance for your response. It is greatly appreciated. Anne Lollis Supervisor-Radiation Protection Fort Calhoun Nuclear Station ________________________________ This e-mail contains Omaha Public Power District's confidential and proprietary information and is for use only by the intended recipient. Unless explicitly stated otherwise, this e-mail is not a contract offer, amendment, or acceptance. If you are not the intended recipient you are notified that disclosing, copying, distributing or taking any action in reliance on the contents of this information is strictly prohibited.