All,
Bruce Power is looking to re-vamp our ALARA Program.  If you are able to
share your ALARA program documents with us it would be greatly
appreciated.  Some specific areas we are interested in:
 
1.  How does your high hazard work planning differ from planning a large
program job?  Do you have an overall ALARA Plan for something like
boiler inspections, with other ALARA Plans for high hazard components of
that work?
 
2.  How do you "challenge" your ALARA Plans to make sure that the
initiatives included in the plan can actually be achieved?
 
3.  What have you done to instill an "every mrem counts" culture at your
plant?
 
4.  How do you integrate an ALARA Plan into the work plans and tasks for
the job?
 
5.  At what dose thresholds do your ALARA Committees approve the ALARA
plans, and what does this approval look like?  
 
6.  Who develops the ALARA Plans at your plant?
 
7.  What are the typical collective doses for your larger outage
programs? 
 
8.  What information is included in your daily RP report to your
leadership team?  What is done with this information?
 
Thank you in advance!
Carrie Porter

RP ALARA Section Manager | Bruce A Radiation Protection & Industrial
Safety Department | 519-361-2673 x16647 | pager: 519-373-5948 |
[email protected]

Reply via email to