At Cook we use 3E-9 uCi/cc with the AMS-4

Thanks,

Derek Hultquist
Health Physicist
D. C. Cook NPP
(269) 465-5901 x2088



From: Lamons, John [mailto:[email protected]]
Sent: Wednesday, May 03, 2017 8:54 AM
To: [email protected]
Subject: [EXTERNAL] [powernet] Setting of Continuous Air Monitors

This is an EXTERNAL email. STOP. THINK before you CLICK links or OPEN 
attachments.

________________________________
I would like to benchmark what set point the industry uses for CAM units (ie 
AMS-4).  We recently had a question from the NRC as to why we set our units at 
10.59 Bq/ft^3  (1.01 e-8 uCi/cc) instead of the posting limit, .3 DAC (about 
3e-9 uCi/cc).  Thanks for the help.

John Lamons
Health Physicist
Comanche Peak Nuclear Power Plant

Reply via email to