Waterford 3 also has an emergent dose form that the work groups fill out. 
Emergent dose is defined as "Work added after schedule freeze and impacts an 
established dose projection."
Below are the signature approvals
Approval Requirements

> 10 mrem

RP Supervisor / RP ALARA Specialist

> 25 mrem

RP Manager / Designee

> 100 mrem

GMPO / Designee

> 250 mrem

ALARA Managers Committee



From: Neil A Szuch [mailto:neil.sz...@dteenergy.com]
Sent: Tuesday, March 06, 2018 10:42 AM
To: 'Powernet@hpspowernet.org'
Subject: [powernet] Quick Hit Benchmark - Emergent Dose Control


EXTERNAL SENDER. DO NOT click links, or open attachments, if sender is unknown, 
or the message seems suspicious in any way. DO NOT provide your user ID or 
password.


I am wondering what the other plants are doing in regards to emergent dose 
authorization. Here at Fermi we have an emergent dose form that work groups 
fill out and need to get approval from RPS, RP General Supervisor, RPM, or 
Plant Manager depending upon the total amount of dose they are requesting.

How are other plants handling the need to add dose during your work weeks?

Who can approve the additional dose? How much can they approve?

We are looking to see if we can improve our process for emergent dose control.

Thanks,
Neil Szuch

DTE Energy
Fermi 2 - Radiation Protection Supervisor
Office: OSB 116
(734)586-4795

"If you can't explain it simply, you don't understand it well enough"
- Albert Einstein

Top 5 Themes: Ideation, Activator, Command, Competition, Deliberative

Reply via email to