Looking for data on reactor cavity decon during an outage:

  *   Plant name
  *   PWR or BWR?
  *   Scheduled duration for cavity decon?  Critical path time?
  *   Methods used for cavity decon?  High pressure spray, heat, wipe, mop, 
removable coating, etc.?
  *   Start & finish rad conditions (dose rates/smears)?
  *   Who performs decon?  Dedicated deconners, RP, maintenance, reactor 
services?

Info from McGuire:

  *   McGuire
  *   PWR - Ice condenser
  *   Phase I = 5 hours (critical path) - 3 passes of high pressure/heat spray 
of shallow end cavity floor and walls up to 8', followed by wipe of walls and 
pushing/mopping water on floor
  *   Phase II = 2 hours (critical path) - dry decon of shallow end cavity 
floor and walls after removal of stud hole plugs and sandbox seals
  *   Rad conditions - Start = 500 mRad, Finish = <50,000 dpm/100cm2 & 10 
mrem/hr
  *   Decon performed by dedicated decon support but considering using RP's in 
the future for better efficiency