I mentioned this before but don't think got a relevant reply - maybe the
question was so dumb it didn't rate one :=)
I have a smidgeon more fact now - my current 10M digit L-L, (34,xxx,xxx)
whic is 8% complete, is giving predicted completion dates varyin from Sep 30
to Dec 25. So this being Aug 7th that's a further duration of from just
under 2 months to just under 5 months .
So .. it seems like the predicted finsih is very dependent on recent
progress ?
Should I be optimistic and assume that keeping the machine humming will
yield the earliest predicted date ?