Hi, I'm new to the area I'm currently in QA reading User Guides. It would
help if I could provide a little more information about the mentioned point
1 on the familiarization with the new voluntrios bugzilla. as I think that
would be the area where I would focus.

regards


2012/11/25 Rob Weir <[email protected]>

> If you are following the Dev mailing list you see that there is
> discussion about the next major release, Apache OpenOffice 4.0, with
> proposed ship dates in the March/April time frame.  We should discuss
> a QA Plan for that release.  My apologies in advance if this is
> already written down someplace.
>
> My proposal:
>
> The major QA activities between now and the release of 4.0 should be:
>
> 1) Ongoing work to review incoming defect reports from users of AOO
> 3.4.1 and earlier releases.  Attempt verification and set severity and
> priority appropriately.  We should probably have 2-3 volunteers
> focusing on this.  This is a great task for new volunteers since it
> helps them gain familiarity with OpenOffice and Bugzilla.
>
> 2) Follow closely the design discussions related to new 4.0 features.
> They are listed on the Wiki (still evolving):
>
> https://cwiki.apache.org/confluence/display/OOOUSERS/AOO+4.0+Release+Planning
> .
>   We need to figure out how we will test these new features.  We need
> a test plan for new features so we can execute on the testing quickly
> once the code is ready to test.
>
> 3) We need to maintain and enhance a "smoke test" that can be run
> frequently (ideally on every build) to verify that it is not broken.
> This should be an automated test that can run in an hour or two.  The
> goal here is to catch new defects very early.
>
> 4) We need to maintain and enhance a "regression test suite" of manual
> and/or automated test cases that thoroughly test all functions of the
> product (ideally).  Depending on how many volunteers are working on
> this, a full regression test pass might take a week or more.
>
> 5) Once "feature freeze" arrives (when all new features are
> implemented) we need to execute regression tests and new feature
> tests.   Depending on how many bugs are found and their severity, this
> might require iteration.  In other words, we might need to run two
> test passes before we're confident we've reached a sufficient quality
> level to release.  Maybe we just plan for two passes?
>
> We also know that releasing is a week long process of voting on a
> Release Candidate, updating the website, etc.
>
> So working backwards, a schedule might look like this:
>
> March 8th : Feature Freeze -- all new features are testable
>
> March 11th-18th: First full test pass (regression and new feature)
>
> March 30th: Translation Freeze (all new translation work done)
>
> April 1st-8th: Second full test pass (regression and new feature)
>
> April 15th: Release Candidate build available, final verification of fixes
> occur
>
> April 22nd: Release Vote starts
>
> April 29th: Release announcement
>
> This is assuming we have enough volunteers that we can do a full test
> pass in one week.  Let's aim for that.  And the whole schedule can
> move depending on when the developers actually reach feature freeze.
>
> The above suggests that QA is working in two phases:  Phase I is
> before feature freeze.  In that time we're focused on processing 3.4.1
> defect reports and preparing for the AOO 4.0 test passes.  And Phase
> II comes in March when feature freeze is hit, when we have 4 or 5
> weeks of intense work to test the AOO 4.0 builds.
>
>
> Regards,
>
> -Rob
>

Reply via email to