On 25/11/2012 Rob Weir wrote:
So working backwards, a schedule might look like this:
March 8th : Feature Freeze -- all new features are testable
March 11th-18th: First full test pass (regression and new feature)
March 30th: Translation Freeze (all new translation work done)
April 1st-8th: Second full test pass (regression and new feature)

Good schedule, but we should consider that it still takes significant time to have translations integrated and binary builds prepared and uploaded. The interval between Feature/Translation Freeze and the following test period should be extended to 5-7 days to be realistic (or, on the other hand, we can try and get faster in integrating translations and preparing/uploading builds, which would be very good!).

Regards,
  Andrea.