On 7 September 2015 at 11:50, Peter Maydell <peter.mayd...@linaro.org> wrote: > Here's a suggested 2.5 release schedule, constructed fairly arbitrarily > by putting a week's margin for slippage in before everybody leaves for > Christmas, and having a four week softfreeze and four week hardfreeze: > > Softfreeze 15 Oct > Hardfreeze 12 Nov > Release 10 Dec > > (these are all Thursdays, and this gives us five and a half weeks til > softfreeze.)
No countersuggestions, so I've removed the bit from the wiki page that said 'provisional'. NB: for this release I want to try recording release-critical issues on the wiki page, so I don't miss them when rolling release candidates. Hopefully this will be a fairly low-effort thing for everybody. thanks -- PMM