I believe that generator wire sizing is not the same as theNEC wiring sizing power coming from the utility. As the wiring /generator shorts the engine will slow there by reducing the output current. IF if IS UL certified, then I see no reason NOT to install the unit. You are not running those wires any distance, no more then 18” to a disconnect device. Large Kohler, Wisperwatt, Onans units do have the 12 wires from the alternator sized at 10 AWG to the breaker. > On May 26, 2016, at 11:26 AM, Chris Mason <cometenergysyst...@gmail.com> > wrote: > > I would find a way to load test the generator, let it run under load for four > hours. If nothing breaks, you don't need to do anything. > > On Wed, May 25, 2016 at 2:39 PM, Kevin Pegg <kp...@energyalternatives.ca > <mailto:kp...@energyalternatives.ca>> wrote: > Hi Daniel, > > > > Appreciate your thoughts on this. > > > > - This wire is contained inside 2" flexible metallic conduit, approx. 3' long > from the alternator to the external breaker. Some of it is in free air, but > most is contained within the conduit. > > - the main breaker is a 100% rated 175A. > > - This is an industrial generator is rated for continual operation at full > load, and my expectations is all the wiring in that unit is suited to that. > Will the site actually draw that? It is entirely possible during heavy loads > & concurrent battery charging that it could well be running at max load for > hrs at a time. > > > > The plastic bushing is easy to remedy, as is the ground lug. > > > > The wire is where I am not sure what to do. Everything I am hearing tells me > that the #4 wire is undersized. So there is a dilemma. If I replace the wires > myself then I believe I have voided the UL certification. But think have made > a safer engine for my client. At the end of the day, it will be me who the > client is calling if there is an issue. > > > > Just for kicks I opened up a couple 25 kW gens and factory wiring was either > # 2 or # 4 for this same purpose. Hmm. > > > > Kevin > > > > From: RE-wrenches [mailto:re-wrenches-boun...@lists.re-wrenches.org > <mailto:re-wrenches-boun...@lists.re-wrenches.org>] On Behalf Of Daniel Young > Sent: May-25-16 7:24 AM > To: 'RE-wrenches' <re-wrenches@lists.re-wrenches.org > <mailto:re-wrenches@lists.re-wrenches.org>> > Subject: Re: [RE-wrenches] Generator factory wiring issues > > > > Kevin, > > > > Based on what the engineer said, I think you both make valid points. > > > > On the 4AWG wire: > > > > Type Z wire (150 C insulation) is rated for 190A based on 2014NEC table > 310.15(B)(19). It’s rated for 120A when in conduit. So is this wire where you > might call it in conduit or free air? I imagine the inside of a generator > enclosure is somewhere in the middle. Also I assume this is Z type or similar > based on the response stating 150 F (I know he meant C) wiring is used. > > > > Is this on a 175A breaker? If so then it should only pull 140A continuous > (maybe it’s a 100% rated breaker?). And that really would not be great for a > generator. Usually we only design for a maximum of 80% loading on a generator > depending on elevation and a few other de-rate factors. In reality do you > expect more than 120A to be a true “continuous” load on this unit. I don’t > know the answer, just worth thinking about. > > > > Plastic bushings: > > > > I sure would want them in a vibrating machine like a generator, but if UL > does not force them to, don’t expect them to include it. (Capitalism at > work). You might be able to use an electricians trick where you cut a PVC > bushing and slip it over the existing wire, then you can thread it in the end > of the fitting and it is 95% as good as a normally installed bushing…. I > would not do it on a new install, but it’s a useful trick when you walk up on > existing mistakes. > > > > Lug: > > > > You could continuity test it to see if it’s a good connection, otherwise that > strikes me as no good either. Just another cost saving step for the manu at > the clients expense in my opinion. It’ll work fine for now, but not likely in > 5-10yrs as corrosion sets in. I’d just throw a star washer underneath if > possible, but it sounds like the stud is not long enough. > > > > So there is a little bitta’ code and a lotta’ opinion. > > > > With Regards, > > > > Daniel Young, > > NABCEP Certified PV Installation ProfessionalTM: Cert #031508-90 > > > > From: RE-wrenches [mailto:re-wrenches-boun...@lists.re-wrenches.org > <mailto:re-wrenches-boun...@lists.re-wrenches.org>] On Behalf Of Kevin Pegg > Sent: Tuesday, May 24, 2016 6:14 PM > To: RE-wrenches <re-wrenches@lists.re-wrenches.org > <mailto:re-wrenches@lists.re-wrenches.org>> > Subject: [RE-wrenches] Generator factory wiring issues > > > > Wrenches, > > > > Recently, we took delivery of a 40 kW LPG generator made by Gillette. > > > > Inspecting the factory wiring of the unit, I had some concerns which are > outlined in detail below, with an engineer's response inline. The concerns > are using #4 wire to pull 175A; no plastic bushings on metallic conduit, and > ground lugs on top of painted surfaces / and insufficiently torqued. > > > > The engineer response has left me somewhat baffled / frustrated in that I do > not feel that actual issues have been addressed. I don't really care what UL > or any other authority tells me - pulling 175A continually for many hrs > through a #4 wire I think is asking for trouble. And my customer won't really > care about what the UL ratings say if they are dealing with a melted > alternator. > > > > Am I missing something here? > > > > Kevin > > > > > > RE: SP-410-1-1LO S/N: > > > > I am responding to the concerns written below both in the capacity as > designer and as U.L. liaison. > > > > We have received this generator, mostly intact. Some freight damage to the > battery support cross member due to forks not extending the full depth of the > crate, and are working with the freight company to resolve that. > > Sorry for the experienced freight damage. > > > > However, there are some SERIOUS and DANGEROUS issues pertaining to the wiring > of the alternator! It is obvious that wiring was not done by an electrician. > > There are no serious or dangerous issues on this (built to U.L. recognized > spec) Gillette Generator as referred to in this writing. And – you are > correct- this wiring, as ‘factory wiring and not ‘field’ wiring, does not > require or use the specific qualifications of a licensed electrician. The > well trained/supervised workers here at Gillette have many years of > experience building the product and are guided as need by a competent > engineering staff. > > > > Specifically: > > > > - Alternator to circuit breaker wiring was done with #4 wire (rated 60A max). > Per your own load chart inside the breaker enclosure (photo attached), that > wire should be 4/0 to carry the 175A that this generator is capable of > producing. > > This observation is incorrect. The load wiring sizing schedule affixed to the > side of the circuit breaker box is for ‘field connectivity’ at 75 deg. F. We > do our ‘factory wiring ‘ on a different schedule using load cabling from the > generator to the top of the circuit breaker rated at 150 deg. F. All of this > cabling has been done, tested and proven by U.L > > > > - There were no plastic bushings (see photo) where the wires exit the metal > conduit. > > The conduit bushing involved is the correct U.L. approved component for the > installation of spiral wound metal conduit required to be installed on ‘open’ > style generator assemblies. A plastic bushing is NOT required as this is > again ‘factory wiring’, not ‘field wiring. > > > > - What would have happened here is the wire heats up due to gross under > sizing, melts the insulation, and shorts it out. Resulting in a fire or > destruction of the brand new alternator, and the associated legal proceedings > involving all parties and a general nightmare for all of us. > > disagree, on several fronts. Referencing the specification standard U.L. > 2200, many times- local inspectors blur the line between its dominance for > standby generator systems and NEC-70 (NEC- code). The former covers ‘factory’ > design wiring on stationary standby generators subject to witness testing by > a U.L. certified representative. The latter applies to ‘field wiring’- that > is anything outside the box including connection conduits, load wiring ( at > 75 deg. F) transfer switches, distribution panes and the like. As resident > designer for the past twenty-six years, I have myself- written eight > standards/code rebuttals successfully, both for U.L. and local inspectors. > Comparing a 4ga, 2ga, 1ga and the like against a different class of wiring > such as a 4/0 would certainly be cause for alarm. But, clearly here the alarm > is unwarranted. > > > > - the ground lug on the alternator was not fastened properly > (a short stud with a nut on it - no way to get proper torque on it - should > be a bolt), and both this lug and the lug inside the breaker enclosure was > fitted on top of a painted surface. Every electrician knows you need to > scrape off the paint so as to allow for proper conductivity. > > This lug is not supplied by us. It is supplied as part of the generator > construction built by Marathon. Marathon generators are certified for U.L. > 1004B- generator assemblies and U.L. 1446 for insulation. This is the > equipment issued as part of that U.L. certified design. as to their design > vs. a ‘bolt’ going into the threads of the hole- if it was really an issue, > it would not have passed their U.L. certification testing. Their generator > assemblies bear their U.L. file certification under R/C (JZGZ2) and listing > (JZGZ). In regards to the paint removal, the engine and generator are cable > grounded to the frame of the generator assembly and serrated hardware is used > during assembly to scratch into the painted surfaces of the boxes and frame. > As you notice in the picture- the threads in the generator housing sleeve- > are not painted. > > > > These are issues that we are able to remedy. But my client, > being very hands on has noticed this and inquired, quite reasonably, as to > why they are paying Energy Alternatives to repair something that they paid > for and should have been delivered properly done in the first place? > > To my findings, there is no warrantable work required. > > > > I think the fairest solution to this is for us to remedy > these defects and to have Collicutt reimburse use for time and materials. I > will complete the work and send you the total bill for compensation unless > you would like to approach this in a different method. We are hoping to go > live with this unit in the next few days once the gas fitting is completed. > > As stated above- Not required. > > > > I hope these responses help clarify the items in question. > > > > > > Regards, > > > > > > > > > _______________________________________________ > List sponsored by Redwood Alliance > > List Address: RE-wrenches@lists.re-wrenches.org > <mailto:RE-wrenches@lists.re-wrenches.org> > > Change listserver email address & settings: > http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org > <http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org> > > List-Archive: > http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html > <http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html> > > List rules & etiquette: > www.re-wrenches.org/etiquette.htm <http://www.re-wrenches.org/etiquette.htm> > > Check out or update participant bios: > www.members.re-wrenches.org <http://www.members.re-wrenches.org/> > > > > > > -- > Chris Mason > NABCEP Certified Solar PV Installer™ > Solar Design Engineer > Generac Generators Industrial technician > > www.cometsolar.com <http://www.cometenergysystems.com/> > 264.235.5670 > 869.662.5670 > Skype: netconcepts > _______________________________________________ > List sponsored by Redwood Alliance > > List Address: RE-wrenches@lists.re-wrenches.org > > Change listserver email address & settings: > http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org > > List-Archive: > http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html > > List rules & etiquette: > www.re-wrenches.org/etiquette.htm > > Check out or update participant bios: > www.members.re-wrenches.org >
> t...@swnl.net > <blocked::mailto:t...@swnl.net%22%20%5Co%20%22blocked::mailto:t...@swnl.net> > www.SWNL.net > <blocked::http://www.swnl.net/%22%20%5Co%20%22blocked::http://www.swnl.net/> > Solarwinds Northernlights > Serving Mid Coast Maine & Northern California > 207-832-7574 Cl. 610-517-8401 > > Blair "TUMP" May > ******** MAINE'S CHARTER ******** > NABCEP "Certified PV Installer" > > ******** MAINE'S CHARTER ******** > Trace Xantrex "Certified" Dealer / Installer" >
_______________________________________________ List sponsored by Redwood Alliance List Address: RE-wrenches@lists.re-wrenches.org Change listserver email address & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org List-Archive: http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html List rules & etiquette: www.re-wrenches.org/etiquette.htm Check out or update participant bios: www.members.re-wrenches.org