You should not have to run a EGC/GEC along the with Array Technologies. When I 
have installed these in the past we always mechanically bond within the 
bicinity of the conduit or box we are running our wiring through. No need to 
non-mechanically attach anywhere.
Whitley Forman    Bannon Specialty Electric Systems    [email protected]

Sent from Yahoo Mail on Android 
 
  On Wed, Apr 18, 2018 at 5:01 PM, 
[email protected]<[email protected]>
 wrote:   Send RE-wrenches mailing list submissions to
    [email protected]

To subscribe or unsubscribe via the World Wide Web, visit
    http://lists.re-wrenches.org/listinfo.cgi/re-wrenches-re-wrenches.org
or, via email, send a message with subject or body 'help' to
    [email protected]

You can reach the person managing the list at
    [email protected]

When replying, please edit your Subject line so it is more specific
than "Re: Contents of RE-wrenches digest..."


When responding to posts within the Digest, be sure to restore the Subject: 
line to the original, and please edit out any extraneous lines from the quoted 
message.
 

Today's Topics:

  1. Re: Looking for insulated #6 bare standoff
      (Dave Angelini Offgrid Solar)


----------------------------------------------------------------------

Message: 1
Date: Wed, 18 Apr 2018 09:59:02 -0700 (PDT)
From: "Dave Angelini Offgrid Solar" <[email protected]>
To: "RE-wrenches" <[email protected]>
Subject: Re: [RE-wrenches] Looking for insulated #6 bare standoff
Message-ID:
    <[email protected]>
Content-Type: text/plain;charset=iso-8859-1

Why is it #6? Usually the solar panels wire size determine Array Teks size
for this wiring. What do they say please?  --Dave

> How about an insulated loop clamp like this one:
> https://www.fastenal.com/products/details/0216763
>
> You can get them in stainless and they have the rubber grommet so it won't
> touch the rack.
>
> On Wed, Apr 18, 2018 at 12:00 PM, Dana <[email protected]> wrote:
>
>> Good Morning Wrenches,
>>
>>
>>
>> I am required to keep the bare #6 copper from touching the aluminum
>> frame
>> work of a Array Technologies tracker where it is not mechanically
>> connected
>> by a pass-through ground clamp on a tracking array [dissimilar metals]
>> and
>> am looking for a lead on an insulated standoff or strap to hold the #6
>> bare
>> copper as it passes from panel to panel and rail to rail. The plans
>> examiner would accept pass through clamps & this is a worst case-spendy
>> solution to this.
>>
>>
>>
>> I have searched the inquired at local electrical warehouse &on the
>> internet and to no avail under ???insulated strap??? & ???insulated
>> cable
>> standoff???.
>>
>>
>>
>> Has anyone else encountered his & what did you use? Where did you source
>> this strap?
>>
>>
>>
>> I remember seeing something like this in the fuzzy past & cannot recall
>> where I saw it or what it was for.
>>
>>
>>
>> Thanks for any suggestions.
>>
>>
>>
>> ------------------------------------------------------------
>> ----------------
>>
>> Dana Orzel                              Great Solar Works, Inc.
>>
>> *C - 208.721.7003                      [email protected]
>> <[email protected]>*
>>
>> Idaho Contractor - # 028765        Idaho PV # 028374
>>
>> NABCEP # 051112-136                      www.solarwork.biz
>>
>> *"Responsible Technologies for Responsible People since 1988"  *
>>
>> *P* Please consider the environment before printing this email.
>>
>>
>>
>>
>>
>> _______________________________________________
>> List sponsored by Redwood Alliance
>>
>> List Address: [email protected]
>>
>> Change listserver email address & settings:
>> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
>>
>> List-Archive: http://www.mail-archive.com/[email protected].
>> org/maillist.html
>>
>> List rules & etiquette:
>> www.re-wrenches.org/etiquette.htm
>>
>> Check out or update participant bios:
>> www.members.re-wrenches.org
>>
>>
>>
>
>
> --
> *Will White*
> Curriculum Developer
>
> [image: Inline image 3]
>
> e: [email protected]
> w: www.solarenergy.org
> p: 802-272-3092
>
> PV Installation Professional
> # 093006-34
> _______________________________________________
> List sponsored by Redwood Alliance
>
> List Address: [email protected]
>
> Change listserver email address & settings:
> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
>
> List-Archive:
> http://www.mail-archive.com/[email protected]/maillist.html
>
> List rules & etiquette:
> www.re-wrenches.org/etiquette.htm
>
> Check out or update participant bios:
> www.members.re-wrenches.org
>
>


Dave Angelini Offgrid Solar
"we go where powerlines don't"
http://members.sti.net/offgridsolar/
e-mail  [email protected]
text 209 813 0060



------------------------------

Subject: Digest Footer

_______________________________________________
List sponsored by Redwood Alliance

List Address: [email protected]

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: 
http://www.mail-archive.com/[email protected]/maillist.html

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
www.members.re-wrenches.org


------------------------------

End of RE-wrenches Digest, Vol 11, Issue 137
********************************************
  
_______________________________________________
List sponsored by Redwood Alliance

List Address: [email protected]

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: 
http://www.mail-archive.com/[email protected]/maillist.html

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
www.members.re-wrenches.org

Reply via email to