Jason, You may want XW pro. It is not much more than XW+ and will have a
better support for what you want in your microgrid. It also has twice the
warranty over xw+.
Dave Angelini Offgrid Solar
"we go where powerlines
don't"
http://members.sti.net/offgridsolar/ [1]
e-mail [email protected]
[2]
text 209 813 0060
On Wed, 11 Sep 2019 18:24:18 -0400, Jason Szumlanski
wrote: That is what I was thinking, but how will the contactor coils
"know" when the ATS switches to inverter power. I'm thinking I need to use
an AUX relay or a series of relays to produce the desired result. I don't
think it will be necessary when going from solar to generator in this case,
but maybe. I guess the question is how to activate the time delay any time
the ATS switches over. That would be the easiest solution maybe. I'm
probably looking at a quad Conext XW+ system here. Even at over 100A @ 240V
continuous rating I'm anticipating some startup issues with all those
motors (I forgot to mention well and pressure pumps also!) Jason
On Wed, Sep 11, 2019 at 5:50 PM Michael Morningstar wrote: Put the
loads on contractors, control the contractors with adjustable time delay
relays. Stagger the timing.
On Sep 11, 2019, at 2:41 PM, Jason Szumlanski
wrote:
In an off-grid situation I'm looking for a strategy to manage
transfer from generator power to inverter power because I have a lot of
high startup load appliances planned for a system. Think 8
mini-refrigerators, one sub-z large refrigerator, and an under-cabinet ice
maker, not to mention air conditioning. I would like to start these loads
in stages if they all call to start up immediately upon system startup or
during ATS switch over. Any ideas? I guess while I'm on the subject I
should ask about my eye-roll, keep-me-up-a-night, giving-me-heartburn
problem with this ice maker. It's going to be outdoors in Florida and they
expect it to make 25-50 pounds of ice per day. I am finding it really hard
to estimate energy use for this appliance. Any ideas (other than the
obvious "don't do it" answer)? Jason Szumlanski Florida Solar Design
Group
_______________________________________________
List sponsored by Redwood
Alliance
List Address: [email protected] [5]
Change
listserver email address &
settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
[6]
List-Archive:
http://www.mail-archive.com/[email protected]/maillist.html
[7]
List rules & etiquette:
www.re-wrenches.org/etiquette.htm [8]
Check
out or update participant bios:
www.members.re-wrenches.org [9]
_______________________________________________
List sponsored by Redwood
Alliance
List Address: [email protected] [10]
Change
listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org [11]
List-Archive:
http://www.mail-archive.com/[email protected]/maillist.html
[12]
List rules & etiquette:
www.re-wrenches.org/etiquette.htm [13]
Check out or update participant bios:
www.members.re-wrenches.org [14]
--
Links:
------
[1] http://members.sti.net/offgridsolar/
[2]
mailto:[email protected]
[3] mailto:[email protected]
[4]
mailto:[email protected]
[5]
mailto:[email protected]
[6]
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
[7]
http://www.mail-archive.com/[email protected]/maillist.html
[8]
http://www.re-wrenches.org/etiquette.htm
[9]
http://www.members.re-wrenches.org
[10]
mailto:[email protected]
[11]
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
[12]
http://www.mail-archive.com/[email protected]/maillist.html
[13]
http://www.re-wrenches.org/etiquette.htm
[14]
http://www.members.re-wrenches.org
_______________________________________________
List sponsored by Redwood Alliance
List Address: [email protected]
Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
List-Archive:
http://www.mail-archive.com/[email protected]/maillist.html
List rules & etiquette:
www.re-wrenches.org/etiquette.htm
Check out or update participant bios:
www.members.re-wrenches.org