Hi Chris,

On 04/30/2016 10:55 AM, Chris Howard - CBR wrote:
> Hi,
>
> I have a condition where there are two carts loaded into the system.
> I want to have the log generator always connect them together.
>
> For example, one cart is Part A, and another cart is Part B.
> I would like to be able to schedule this with the log generator
> so that Part A is always followed by Part B without requiring my
> intervention.
>
> The only thing I see in the RDLibrary which may hint at
> a solution is labeled "outcue" and I don't know what that means.
>
> Should I build a macro:  Play cut 1, play cut 2
> and then let log builder schedule the macro?
>
>
I wouldn't do anything special with RDLibrary or macros. I'd simply
build an event (in RDLogManager) that includes both carts either in the
Pre-Import Carts section, the Post-Import Carts section, or one in
Pre-Import and one in Post-Import. In all three of these cases you'd
leave the Import section blank. Make sure to set the Timed Start type
appropriately for the event.

Then place the event at the appropriate position in all the clocks in
which you want to schedule the event. And place those clocks in the
appropriate hours in your Service Grid(s).

When you run Generate Logs with RDLogManager the clocks with that event
will pull those two specific carts and schedule them back to back in the
log.

Hope this helps!

  ~David Klann


Attachment: signature.asc
Description: OpenPGP digital signature

_______________________________________________
Rivendell-dev mailing list
[email protected]
http://caspian.paravelsystems.com/mailman/listinfo/rivendell-dev

Reply via email to