Subject: Re: SAF: Insulation resistance and hipot tests
Folks:
EN 60204-1 also specifies an insulation resistance test.
Depending on the standard, they tell you the sequence of the various safety
tests.
For example, in EN 60204-1, clause 19.1
Folks:
EN 60204-1 also specifies an insulation resistance test.
Depending on the standard, they tell you the sequence of the various safety
tests.
For example, in EN 60204-1, clause 19.1 (the test clause) states:
When these test are performed, it is recommended that they follow the
sequence
Hello Martin,
I don't have the answer to your question, but do caution that the First
Test to be run (if the DUT is grounded) is the Ground Continuity Test (for
test-operator protection).
Regards, Art Michael
* * * * * * * * * * * * * * * * * * * * * *
*
Group,
A reader asked about the order of performing safety tests.
Should he perform insulation resistance tests before or after
hipot tests? The reader didn't say what type of product he's
testing, but I can ask.
Thanks,
/\