Re: Lucene 2.2 - Suggested schedule

2007-06-06 Thread Doron Cohen
-- Feature freeze from Wednesday (06/06) All features must be checked in by end of Tuesday. On Wednesday I will Michael, is there a need to hold commits to trunk while the new branch is created? (This is with LUCENE-912 and LUCENE-913 in mind - I think they can wait for 2.3, there would

Re: Lucene 2.2 - Suggested schedule

2007-06-06 Thread Michael Busch
Doron Cohen wrote: Michael, is there a need to hold commits to trunk while the new branch is created? No, normal trunk development may continue as usual. (This is with LUCENE-912 and LUCENE-913 in mind - I think they can wait for 2.3, there would always be new issues.) I haven't

Re: Lucene 2.2 - Suggested schedule

2007-06-06 Thread Yonik Seeley
On 6/6/07, Michael Busch [EMAIL PROTECTED] wrote: I haven't branched the trunk yet (I will send a different mail to this list afterwards). Since the patches are in place we might want to commit LUCENE-912 and LUCENE-913 before? +1, these are medium-serious bugs with fixes that look unlikely to

Re: Lucene 2.2 - Suggested schedule

2007-06-06 Thread Doron Cohen
Michael Busch wrote: I haven't branched the trunk yet (I will send a different mail to this list afterwards). Since the patches are in place we might want to commit LUCENE-912 and LUCENE-913 before? If there are no objections I plan to commit it later today.

Re: Lucene 2.2 - Suggested schedule

2007-06-06 Thread Michael Busch
Doron Cohen wrote: If there are no objections I plan to commit it later today. +1. Thanks for taking care of these, Doron! I'm working on LUCENE-908 in parallel. After all three are committed (908, 912, 913) I will make the branch.

Re: Lucene 2.2 - Suggested schedule

2007-06-06 Thread Michael Busch
Doron Cohen wrote: Since the patches are in place we might want to commit LUCENE-912 and LUCENE-913 before? If there are no objections I plan to commit it later today. 912 and 913 are committed. Great job, Doron! Thank you! Alright, everything seems to be in place. Good timing! I

Re: Lucene 2.2 - Suggested schedule

2007-06-05 Thread Grant Ingersoll
+1 If this new process goes well (which it seems to be), it should be added to the How To Make a Release Thanks, Michael, for all your hard work on this. -Grant On Jun 4, 2007, at 11:35 PM, Michael Busch wrote: Hello everyone, I'd like to suggest a schedule here for the Lucene 2.2

Lucene 2.2 - Suggested schedule

2007-06-04 Thread Michael Busch
Hello everyone, I'd like to suggest a schedule here for the Lucene 2.2 release: -- Feature freeze from Wednesday (06/06) All features must be checked in by end of Tuesday. On Wednesday I will branch the trunk and we will have a feature freeze on the branch. Then only Jira issues with Fix