Eugene,
To increase focus and ensure velocity increase, we decided to descope the
following patch from the current release cycle [1]. This willl have minor
effect on supported use cases, but will allow us to focus on the required
parts [2] [3].
[1] https://review.openstack.org/#/c/203537/
[2] htt
Oleg, thanks for the provided information. As discussed verbally, most
core reviewers are now busy with fixing critical bugs, so you might get
delayed responses. Keeping in mind, let's target Wednesday, Aug 5 as the
last deadline. With that said, let's minimize review iterations so core
reviewe
Team,
I'd like to inform you about status of FF Exception for Cluster Upgrade
feature.
The due date for the exception was Jul 30th. We had 4 patches to merge in
the beginning of the work.
During review it was decided that changes to the core of Nailgun should be
split into separate CR, making it