On 12/19/2017 01:53 AM, James E. Blair wrote:
Ian Wienand writes:
There's a bunch of stuff that wouldn't show up until live, but we
probably could have got a lot of prep work out of the way if the
integration tests were doing something. I didn't realise that although
we run the tests, most of
Ian Wienand writes:
> There's a bunch of stuff that wouldn't show up until live, but we
> probably could have got a lot of prep work out of the way if the
> integration tests were doing something. I didn't realise that although
> we run the tests, most of our modules don't actually have any test
On 12/16/2017 10:17 AM, Clark Boylan wrote:
> As the week ends there are a few services that are still in progress.
> Hope to get them done shortly:
>* etherpad.openstack.org
>* ethercalc.openstack.org
>* status.openstack.org
Working on these, all pretty much held up due to nodejs is
+1, my day to day tends to be a bit hectic so it's hard to commit to a full
sprint but I have time here and there to help move things along.
David Moreau Simard
Senior Software Engineer | Openstack RDO
dmsimard = [irc, github, twitter]
On Dec 15, 2017 8:09 PM, "James E. Blair" wrote:
> Clark B
Clark Boylan writes:
> Hello everyone,
>
> Just wanted to quickly recap what we got done this week during our
> control plane upgrade to Xenial sprint.
Thanks!
Now that this is over, I wonder if we should start a 'marathon' (as
opposed to a sprint) to finish the rest of the servers?
Now that w
Hello everyone,
Just wanted to quickly recap what we got done this week during our
control plane upgrade to Xenial sprint.
Prior to the sprint we had a few systems running on Xenial:
* Everything zuulv3
* All of the new nodepool launchers and image builders
* The translate servers
* The p