Toby,

That is how it works by default. If you look in the Business Manager
workflow processes you will see that only one is marked active at any
one time. If it is sent back, it is removed from the task list of the
person sending it back.

Lanny Udey
Hofstra University

>>> Toby Tremayne <[EMAIL PROTECTED]> Friday, August 11, 2000
>>>
imagine I had a three step workflow (3 tasks)

task one gets completed and is marked as finished.  Task 2 is marked as
begun.(active)

the task 2 user logs in completes the task and it is sent back to redo
task 1.

[ obviously this restarts task 1, but what I want to know is does this
mean task 2 remains active?  or do I finish task two and just get it to
begin again when task one has been redone?]

the point of all this is I have a couple of stages which might need to
pass back to a predecessor, but I want to know if I can work it so only
one task is ever active at one time......



Toby Tremayne
Code Poet and Zen Master of the Heavy Sleep
Show-Ads Interactive Pty Ltd
359 Plummer St
Port Melbourne
AUST VIC 3207
+61 3 9245 1247
------------------------------------------------------------------------------
To Unsubscribe visit 
http://www.houseoffusion.com/index.cfm?sidebar=lists&body=lists/spectra_talk or send a 
message to [EMAIL PROTECTED] with 'unsubscribe' in the body.

Reply via email to