I Really appreciate the knowledge you all are sharing.  Really.

How we will get it dug, is the debate.  Water company
will dig.  Their bid is $250 per ft for 300 ft though.  They
assured me this would include the hot tap, pipe and tamping.

So, I went to some guys who were backhoeing streets --
just down from the office.  What information
I did get led me to $35 per ft.  They said they would
throw a single tooth in-place of the bucket and rock on.
I didn´t expect them to include the hot tap, though.

Water company charges a premium, as they
don´t want the work.  How far over what a
legitimate private excavator would bid,
20%?  $200/ft?  I am still waiting for call backs.

RS Means suggest about $100/LF with blasting,
excavating, pipe, fill and compaction of 100 BCY.

Add the cost of a one-shank ripper and 20% inefficiency
and we are at $135/LF.  Figure inflation at 4% for 2 years-
We get about $145/LF.

but that is wide-eyed guessing.  I could be abusing the Means.

Scot Deal
Excelsior Fire





> if you mean rock, as in ROCK then $85/ft. is a pittance.  Hard-pan can be
> bad enough that a big hoe or blasting could be required.  Real rock strata
> requires a track hoe with an incredibly powerful breaker AND explosives.
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum

To Unsubscribe, send an email to:[EMAIL PROTECTED]
(Put the word unsubscribe in the subject field)

Reply via email to