We have a project (>100,000 sq ft, 35' deck) where we have ESFR's throughout at 
the ceiling.

There is a 10,000 sq ft mezzanine (12' to the floor) in the middle of the 
warehouse. No walls separating the area below the mezzanine from the remainder 
of the building.

I believe that we need a draft stop around the perimeter of the mezzanine, 
since we will not be having ESFR's below the mezz.

#13 says that we need this draft stop when we have ESFR adjacent to standard 
heads. Is the area below the mezzanine really "adjacent" to the ESFR's at the 
roof?

Greg Lindholm