On jobs where hose valves are required on the alternate landing, where are 
you guys placing the floor control valves in relation to the standpipe? 
For example, do you leave the standpipe on the alternate landing and run 
up to the main landing and place the floor controls there?  Do you put the 
controls on the alternate landing and run the sprinkler up to the main 
landing and into the ceiling?  Do you use separate risers for standpipes 
and sprinklers? ...............

Seems to me there's a bunch of different placement options but just wanted 
to see what others thought was best. 

John Kaminski
Burt Hill
724-431-1388
http://www.burthill.com