I don't think you have to include outside hose flow. But, you said this was military. As such, you will most likely have a separate test header with (1) 2.5" hose vale for every 250 gpm system demand. That has at least been my experience. Travis Mack, SET MFP Design, LLC www.mfpdesign.com
Sent on the Sprint® Now Network from my BlackBerry® -----Original Message----- From: "Gregg Key" <[email protected]> Sender: [email protected]: Tue, 21 Jun 2011 10:35:36 To: <[email protected]> Reply-To: [email protected] Subject: Backflow forward flow test Ok now that I got past that, Any reason that the 2" main drain could not be used if the required flow could be achieved. System demand + hose allowance? C.Gregg Key, SET Key Fire Protection Services,Inc Project Manager (O) 706-790-3473 (C) 706-220-8821 _______________________________________________ Sprinklerforum mailing list [email protected] http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum For Technical Assistance, send an email to: [email protected] To Unsubscribe, send an email to:[email protected] (Put the word unsubscribe in the subject field) _______________________________________________ Sprinklerforum mailing list [email protected] http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum For Technical Assistance, send an email to: [email protected] To Unsubscribe, send an email to:[email protected] (Put the word unsubscribe in the subject field)