Subject: Multiple Hydrostatic Tests

We have run across an interesting situation at a California Hospital. The
IOR is suggesting that we will be required to hydro the systems twice, once
at rough-in for a “performance test” and again near final as an “acceptance
test”. His logic is that all appurtenances are not installed and in place
at the time of rough-in which is required by the code, thus removing plugs
and installing sprinklers in flex drops he considers a significant
modification or “more than a minor” modification, so test twice.


Anybody have any interpretations or documents that would refute this?


Gary Stites
*805-769-GMAN*
RLH <http://www.rlhfp.com>
Google+ <https://plus.google.com/101832074405776300082/posts?hl=en>
Mr. Ricky <http://www.mrricky.net>
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org

Reply via email to