13 or 13R?

Check section 8.15 to see if they fit any of the exceptions.

Matt Grisé PE*, LEED AP, NICET II
Vice President - New Construction
Alliance Fire Protection
130 w 9th Ave.
North Kansas City, MO 64116

*Licensed in KS & MO

913.888.0647 ph
913.888.0618 f
913.526.7443 cell
www. AFPsprink.com


From: Sprinklerforum [mailto:[email protected]] On 
Behalf Of Brian Harris
Sent: Friday, February 24, 2017 11:07 AM
To: [email protected]
Subject: Wood Soffits

We're working on a wood framed building that has several "bump-out's/soffits" 
that will be covered with GWB. Are heads required in all of these ?