-------- Original Message -------- Subject: [swinog] Upgrade Main Power Supply Date: Thu, 3 Jul 2003 17:31:29 +0100 From: Frits van der Graaff <[EMAIL PROTECTED]> Reply-To: [EMAIL PROTECTED]
IXEurope is writing to you to inform you that as part of the remedial action to prevent a repeat of Monday evenings power incident, the landlord and IXEurope have arranged to have EWZ/Deltasys attend site to carry out an upgrade to the Main Power supply to the building by 25% at 0:00 tonight.
This will require the Datacentre to be running on UPS Batteries for up to 5minutes whilst EWZ perform this operation. No power outage is expected , however preparations will be made by the technical staff in case of any problems or in the unlikely event of another outage.
A new, larger capacity, temporary Diesel Generator has been ordered and is expected to be online by Wednesday the 9th of July. We are upgrading the power supply before the temporary Diesel Generator is installed because we believe that the risk of problems during the upgrade operation are small compared to the risk of an outage between now and when the Generator is brought on-line due to forecasted increase in ambient temperature in the Zurich area over the weekend.
Yours sincerely,
Frits van der Graaff General Manager Switzerland
IXEurope Telehouse Facilities AG Hardstrasse 235 CH- 8005 Z�rich Switzerland *Tel.:* +41-(0)-1-355 69 00 ***Tel. direct:* +41-(0)-1-355 69 20 ***Fax:* +41-(0)-1-355 69 99* * *****Mobile: * +41-(0)-79-622 62 29 ***email:* [EMAIL PROTECTED] <mailto:[EMAIL PROTECTED]>_
-- Mit freundlichen Gr�ssen
Candid Aeby Internet Pipeline AG Hardstr. 235 8005 Z�rich Tel +41 1 277 75 55 / Fax +41 1 277 75 50
http://www.pipeline.ch [EMAIL PROTECTED]
---------------------------------------------- [EMAIL PROTECTED] Maillist-Archive: http://www.mail-archive.com/swinog%40swinog.ch/