Hi list,

Before leaving for a holiday vacation last week, I started a very long
tahoe backup operation (>10GB) with some very large files.  And while away,
a second tahoe backup operation was started from a cron.  This second job
should have been pretty short as it was just an incremental backup of an
area that had already been backed up before.

Alas, both of these backups hung.  It looks like we're missing a timeout
somewhere, as it's been several days since anything's happened, and this is
what my node's status page says for Active Operations:

Type    Storage Index   Helper?         Total Size      Progress        Status
mapupdate MODE_WRITE    twfhdmkbsoidlnf3zijrcut7jm      No      -NA-    0.0%    
Sending
6 initial queries
publish         dt5jrwb3ck2yt3tp7etuw6aply      No      0B      90.0%   Sending 
Shares: 9
placed out of 10, 1 messages outstanding

And it's stuck here, never changing.  (In my process list I see two tahoe
backup processes.)

What can I do at this point?  Do I need to kill and restart?  That would
be no big deal for the incremental backup, but I worry that restarting the
backup of large files would mean uselessly re-uploading several gigabytes
of data that are already on the grid.

-- 
Kyle Markley
_______________________________________________
tahoe-dev mailing list
[email protected]
http://allmydata.org/cgi-bin/mailman/listinfo/tahoe-dev