intrigeri:
> intrigeri wrote (18 Jan 2014 10:01:53 GMT) :
>> So, the schedule for the next steps towards 0.22.1 becomes:
> 
>>   2014-02-01   package new Firefox ESR
>>   2014-02-02   build and upload final ISO
>>   2014-02-03   test final ISO
>>   2014-02-04   release
> 
>> Can anyone else than me take over the Release Manager role for these
>> last steps? Worst case, I can do it, or part of it, but it's quite
>> painful for me.
> 
> OK, I'll do it, then.
> 
>> Core developers: ASAP, please volunteer for the test days, or make it
>> clear that you can't make it, so we can reschedule slightly if needed.
>> Thanks in advance!
> 
> Ping?

I can do tests on the 3rd.



Attachment: signature.asc
Description: OpenPGP digital signature

_______________________________________________
tails-dev mailing list
[email protected]
https://mailman.boum.org/listinfo/tails-dev

Reply via email to