On Tue, Jan 28, 2014 at 04:47:02PM +0000, [email protected] wrote: > intrigeri: > > intrigeri wrote (18 Jan 2014 10:01:53 GMT) : > >> So, the schedule for the next steps towards 0.22.1 becomes: > > > >> 2014-02-01 package new Firefox ESR > >> 2014-02-02 build and upload final ISO > >> 2014-02-03 test final ISO > >> 2014-02-04 release > > > >> Can anyone else than me take over the Release Manager role for these > >> last steps? Worst case, I can do it, or part of it, but it's quite > >> painful for me. > > > > OK, I'll do it, then. > > > >> Core developers: ASAP, please volunteer for the test days, or make it > >> clear that you can't make it, so we can reschedule slightly if needed. > >> Thanks in advance! > > > > Ping? > > I can do tests on the 3rd.
Can do that too. bert. _______________________________________________ tails-dev mailing list [email protected] https://mailman.boum.org/listinfo/tails-dev