[email protected] wrote (18 Jul 2014 21:01:02 GMT) :
>>   2014-08-12   Feature freeze
>>   2014-08-13   Tag 1.1.1-rc1 in Git.
>>                Build and upload 1.1.1-rc1 ISO/IUKs.
>>   2014-08-14   Test 1.1.1-rc1
>>   2014-08-15   Release 1.1.1-rc1

> Aren't we supposed to skip RC for a point release? Or did I miss something?

Indeed, you're entirely right in principle. In practice, in the recent
past, quite often we've not skipped it.

For 1.1.1, I expect we'll have/want to merge quite a few regression
fixes. Some might be invasive. I think it's safer to schedule time for
a RC, and then decide (around August 5) to skip it if things
look safe.

Fair enough?

Cheers,
-- 
intrigeri