Hi, here is the update.

As the SSA engineer was not responding properly and the contractor who has
done work till now  is absconding from me, I met district collector
yesterday. He spoke with S.E Mr. Bhojaraju and asked him to close it soon.

Later i went to SSA office as they were calling me. SSA engineers now
suggest to get the work done by another contractor but they are asking us to
pay for the material cost for now. They say we debit the amount once SSA
releases fund after work completion.

The amount they are asking us to pay to new contractor is 20k. Actually work
may cost around 30 to 50k. I am not sure of the actuals. They are suggesting
to record the present work so that we do not pay extra to the new
contractor.

But on the other side, we have already incurred additional cost with the
condition that we get  it adjusted from the SSA funds.

for the people who do not hv enough background, we got one installment
payment from SSA around 1.4 lakh that we already paid to the contractor who
has done the work till now.


If members agree to proceed further to pay 20k to another contractor for the
remaining work, we can proceed further.

Please share your inputs. No criticism please, these guys(SSA engineers and
the contractors) are real rogues and its been getting delayed because of
them. I am just trying to see completion ASAP (1 or 2 weeks max) but again
it depends.

Thanks, Harinath