Thank you Harinath Garu for the update and pursuing it till extent of
meeting collector.

Since, we are sure that we will get back from SSA after completion, I donot
see any risks in expending another 20 K. However, I am not on top of the
funds available in TMAD acct. Let Satya krishna / Prasanthi respond. Thank
you.

Regards,
Ravi.

On Sat, Jul 31, 2010 at 9:40 PM, harinath <[email protected]> wrote:

>
>
> Hi, here is the update.
>
> As the SSA engineer was not responding properly and the contractor who has
> done work till now  is absconding from me, I met district collector
> yesterday. He spoke with S.E Mr. Bhojaraju and asked him to close it soon.
>
> Later i went to SSA office as they were calling me. SSA engineers now
> suggest to get the work done by another contractor but they are asking us to
> pay for the material cost for now. They say we debit the amount once SSA
> releases fund after work completion.
>
> The amount they are asking us to pay to new contractor is 20k. Actually
> work may cost around 30 to 50k. I am not sure of the actuals. They are
> suggesting to record the present work so that we do not pay extra to the new
> contractor.
>
> But on the other side, we have already incurred additional cost with the
> condition that we get  it adjusted from the SSA funds.
>
> for the people who do not hv enough background, we got one installment
> payment from SSA around 1.4 lakh that we already paid to the contractor who
> has done the work till now.
>
>
> If members agree to proceed further to pay 20k to another contractor for
> the remaining work, we can proceed further.
>
> Please share your inputs. No criticism please, these guys(SSA engineers and
> the contractors) are real rogues and its been getting delayed because of
> them. I am just trying to see completion ASAP (1 or 2 weeks max) but again
> it depends.
>
> Thanks, Harinath
>
>
>
>
>
>
>
>  
>