On Mon, 2010-12-13 at 10:17 -0500, Chris Nelson wrote: > I announced the Trac-jsGantt plugin on 12/6. Since then I've gotten some > valuable feedback from Roger Oberholtzer and "yoheeb" (Thanks, guys!) and > refined a few features.
I have finally had time to install the latest. We are moving forward. I have a milestone that is due March 1, 2011. It is the only milestone defined that is not already completed and closed. In the chart, for the milestone, a triangle is placed at Dec 31. 2010. Shouldn't the triangle be at Match 1, 2011? I still need to play with the actual entries. But I think that is more a matter of me adding dates and such to the tickets. -- Roger Oberholtzer -- You received this message because you are subscribed to the Google Groups "Trac Users" group. To post to this group, send email to [email protected]. To unsubscribe from this group, send email to [email protected]. For more options, visit this group at http://groups.google.com/group/trac-users?hl=en.