On Mon, 2010-12-13 at 10:17 -0500, Chris Nelson wrote:
> I announced the Trac-jsGantt plugin on 12/6.  Since then I've gotten some 
> valuable feedback from Roger Oberholtzer and "yoheeb" (Thanks, guys!) and 
> refined a few features.


I have finally had time to install the latest. We are moving forward.

I have a milestone that is due March 1, 2011. It is the only milestone
defined that is not already completed and closed. In the chart, for the
milestone, a triangle is placed at Dec 31. 2010. Shouldn't the triangle
be at Match 1, 2011?

I still need to play with the actual entries. But I think that is more a
matter of me adding dates and such to the tickets.


-- 
Roger Oberholtzer

-- 