Roger Oberholtzer wrote:
> On Mon, 2010-12-13 at 10:17 -0500, Chris Nelson wrote:
>> I announced the Trac-jsGantt plugin on 12/6.  Since then I've gotten
>> some valuable feedback from Roger Oberholtzer and "yoheeb" (Thanks,
>> guys!) and refined a few features.  
> 
> I have finally had time to install the latest. We are moving forward.
> 
> I have a milestone that is due March 1, 2011. It is the only milestone
> defined that is not already completed and closed. In the chart, for
> the milestone, a triangle is placed at Dec 31. 2010. Shouldn't the
> triangle be at Match 1, 2011?

Yes, I'd expect so.  Can you show me?  Maybe a screen shot of the Gantt
with the End Date column shown and the diamond in the wrong place?

> I still need to play with the actual entries. But I think that is
> more a matter of me adding dates and such to the tickets.

We've put this in our production environment this week so I may be
making a round of tweaks soon based on my users' feedback.

-- 
You received this message because you are subscribed to the Google Groups "Trac 
Users" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/trac-users?hl=en.

Reply via email to