On 2016-04-14 20:34, Sergi Almacellas Abellana wrote:
> Hi,
> 
> I'm testing the new production_work module and I see that the cicles cost is
> not added to the output unit price automatically [1], so if it is not added
> manually you can not finish the production due to uneven costs.
> 
> So I'm wondering why we force the user to manually enter the cost on outputs
> if we can automatically add them when the production is done.

Because we don't know the cost of the cycle in advance and we don't
really know the part of the cost to add which comes from the cycle and
not from other changes.

-- 