> On 2016-04-14 20:34, Sergi Almacellas Abellana wrote:
> > Hi,
> > 
> > I'm testing the new production_work module and I see that the cicles cost is
> > not added to the output unit price automatically [1], so if it is not added
> > manually you can not finish the production due to uneven costs.
> > 
> > So I'm wondering why we force the user to manually enter the cost on outputs
> > if we can automatically add them when the production is done.
> 
> Because we don't know the cost of the cycle in advance and we don't
> really know the part of the cost to add which comes from the cycle and
> not from other changes.

What about the use of standard costs for certain operations?

-- 
You received this message because you are subscribed to the Google Groups 
"tryton" group.
To view this discussion on the web visit 
https://groups.google.com/d/msgid/tryton/trinity-d77aed6f-7839-4361-a34b-48df77356996-1460709928522%403capp-gmx-bs71.

Reply via email to