Hi, On Tue, May 12, 2009 at 5:56 PM, Thilo Goetz <[email protected]> wrote: > * Getting releases approved by the incubator PMC is > intensely painful.
I should be able to help with that. > * The version number: we could go with 2.3, or 2.2.3. > Arguments could be found for each, I don't have a strong > opinion. The number of improvements and new features tagged in Jira for the next release suggest that it should be called 2.3, though I'm not too familiar with your version numbering strategy. > Time frame (straw man proposal): > > 6/15 end of coding, only bug fixes after this point > 6/22 end of testing, create distribution and submit for > release vote > 6/30 release An alternative would be to create a release branch on 6/15 and selectively merge only bug fixes from trunk after that. This approach has the benefit that it allows normal development to continue in trunk while the release is being prepared. Not sure if it's worth the extra trouble though. BR, Jukka Zitting