with an upgrade like this in my experience it's usually less than 30 days to 
provide. Key thing is ensuring you CP places the order correctly.

Sent from my iPhone

On 24 Jun 2017, at 12:00, Wojciech Lesiak 
<[email protected]<mailto:[email protected]>> wrote:

Hi all,

I have ordered an leased line upgrade (bearer upgrade from 100 to 1000mbit but 
is over existing media/fibre) from my upstream over 8 weeks ago. Now I have 
been informed that the provisioning time is 30 working days form the time when 
the order is placed with Openreach.
Is this standard practice ?