On Mar 26, 2009, at 10:04 PM, Steve Appling wrote:

Perhaps I am missing something simple, but I can't figure out how to run just the tests in a specific project for a multi-project system.

If I specify :projectname:test it appears to run all tests in dependent project first. This makes it very tedious when you are trying to do development on a module with lots of dependencies.

We know that this is a paint point in 0.5 It will be fixed in 0.6. In 0.6 you will be able to define whether tests should be executed for dependent projects or not.

- Hans

--