If I am understaning what you are trying to do, I'd suggest to use the
new "quick start all tasks" link in the production run screen.
Then you'll have a chance to put into warehouse (using the "stock in"
field) the quantity produced; you can submit the quantity in several
steps: in this way all the tasks will stay open until you have
manufactured all the products.
Jacopo
On May 30, 2008, at 6:20 PM, Daniel Riquelme wrote:
I have a question regarding task sequencing.
I have a route with a couple of tasks associated with it.
Every thing works fine when creating a production run of 1 unit, but
when
selecting a larger quantity, each task repeats itself to build the
quantity
selected, then the second task starts.
Is this behaviour related to the formula I'm using ?
If it's not, how can I get OFBiz to run the first task once and then
the
second, and repeat the whole process until the selected quantity gets
manufactured ?
Best Regards,
Daniel Riquelme