If you need to get the estimated end date for each product produced
then what you really need is to create one separate production run for
each product you have to manufacture.
Jacopo
On May 30, 2008, at 7:34 PM, Daniel Riquelme wrote:
Yes, but I won't get the correct fixed asset schedule or the correct
estimated end date.
On Fri, May 30, 2008 at 1:08 PM, Jacopo Cappellato <
[EMAIL PROTECTED]> wrote:
If I am understaning what you are trying to do, I'd suggest to use
the new
"quick start all tasks" link in the production run screen.
Then you'll have a chance to put into warehouse (using the "stock in"
field) the quantity produced; you can submit the quantity in
several steps:
in this way all the tasks will stay open until you have
manufactured all the
products.
Jacopo
On May 30, 2008, at 6:20 PM, Daniel Riquelme wrote:
I have a question regarding task sequencing.
I have a route with a couple of tasks associated with it.
Every thing works fine when creating a production run of 1 unit,
but when
selecting a larger quantity, each task repeats itself to build the
quantity
selected, then the second task starts.
Is this behaviour related to the formula I'm using ?
If it's not, how can I get OFBiz to run the first task once and
then the
second, and repeat the whole process until the selected quantity
gets
manufactured ?
Best Regards,
Daniel Riquelme