I just want to accomplish one manufacturing process as follows :

     A------------------------>B--------------------->Finished product
  (requries             (requires raw
   raw material        material as c
   a and b and         and d and
    outputs c)           outputs finished
                             product)


   here A and B are the routing tasks. What I have done is I have defined c
as "work in progress" but when I create the production run for finished
product it does not shows the requirement of a and b whether BOM is defined
for finished product or for c and finished product both. Someone please
share your thoughts on this.
here I have created

   - Ram materials as RAW_A, RAW_B, RAW_D and RAW_C as work in progress.
   -  I have created two routing tasks as TASK_A and TASK_B. Task_A uses
   RAW_A and RAW_B as raw material to      produce RAW_C. And, TASK_B uses
   RAW_C and RAW_D as raw materials to produce the finished good.
   - Then I have created routing called RoutingA-B having routing task A and
   B.
   -  Then I have created BOM for finished product only mentioning raw
   materials RAW_A, RAW_B for sequence 1 and RAW_C and RAW_D for sequence 2.
   -  Now creating a production run for finished product in jobshop it does
   not shows the requirement for RAW_A and RAW_B.
   - Then I have also created BOM for RAW_C and finished product separately
   also and it shows the dependent processes between the two.
   - also when I RAW_C get produced in the production run it does not show
   as inventory in facility is it due to its status as Work in Progress ?

 Please suggest the way out...